An Overview of Marple Locks

Click the buttons below and images will be displayed. Each lock has two images; one is the bridge over the tail of the lock, while the other is the lock itself. Buttons displaying the tail bridge have the suffix 't'. All photographs are dated 1978.

 

The rise of a lock is taken to be the vertical height of its bypass (or overflow) weir above that of the bypass weir of the lock below it. In the the case of the Peak Forest Canal the Deposited Plan of the Marple flight recorded the overall vertical rise to be 212 feet but at this stage the number of locks to be built had not been agreed upon. The Committee of the Peak Forest Canal Company recognised that the flight was to be extraordinarily steep and they requested their engineer, Benjamin Outram, on two occasions to reconsider the number of locks in the flight. In the event, Outram settled on their being 16 locks in the flight, with an average rise of 13 feet 1 inch, which meant that the overall rise was to be 209 feet 4 inches.

Nevertheless, as built, the flight rose by 209 feet 5 inches with the rise of individual locks varying between 12 feet 7 inches and 13 feet 6 inches. The two deepest locks at Marple are Nos. 8 and 14, each with a rise of 13 feet 6 inches.

Statistics of Marple Locks based on an Ordnance Survey of April 1894

Above Ordnance Datum at the summit of the locks: 517.98 feet (517 feet 11.76 inches)
Above Ordnance Datum at the foot of the locks: 308.38 feet (308 feet 7.08 inches)

Vertical rise between the foot and the summit: 209.39 feet (209 feet 4.68 inches, say, 209 feet 5 inches)
Distance between the foot and summit of the locks: 1 mile 3 chains
Gradient or slope of the locks: 1 in 26.16 (3.825%)

Maximum rise: Locks 8 and 14 at 13 feet 6 inches
Minimum rise: Lock 10 at 12 feet 7 inches

Maximum length: Locks 5, 9 and 14 at 77 feet 6 inches
Minimum length: Lock 10 at 76 feet

Maximum width: Lock 9 at 8 feet 3 inches
Minimum width: Lock 13 at 7 feet 7 inches

Maximum capacity: Lock 14 at 52,135.35 UK gallons
Minimum capacity: Lock 13 at 45,970.43 UK gallons

Maximum weight of water: Lock 14 at 232.75 tons
Minimum weight of water: Lock 13 at 205.23 tons

Total capacity of all 16 locks: 791,217.61 UK gallons
Total weight of water in all 16 locks: 3,532.22 tons

Average capacity of each lock: 49,451.10 UK gallons
Average weight of water in each lock: 220.76 tons

Average rise of each lock: 13 feet 1 1/16 inches

These locks are among the deepest narrow locks in the country and the Upper Peak Forest Canal is the second highest canal pound, the highest being the summit pound of the Huddersfield Narrow Canal.

Due to severe financial constraints on the Peak Forest Canal Company, the construction of Marple Locks took many years to complete and to overcome the delay the temporary Marple Tramway was built to bypass the unfinished locks.

Key Dates

October 1795: The Committee instruct Benjamin Outram to stake out the line of Marple Locks but groundwork only commenced on locks 1, 2, 3 and 4.
July 1796: The Committee considered that it was not entirely obligated to building locks and it examined a range of options. In contradiction to this, the site of lock 16 (Top Lock) was agreed upon and this determined the location for the construction of Samuel Oldknow's lime kilns.
February 1797: The Committee resolved that locks shall be built at Marple and groundwork started on locks 6, 7, 8 and 9.
March to October 1797: Groundwork started on locks 13, 14 and 15. There was no mention of lock 16 and it can be deduced that this was in an advanced stage of construction.
October 1797: All work on the locks was suspended and it was decided to build the temporary Marple Tramway.
January 1798: Work commenced on construction of the tramway to bypass the unfinished locks.
May 1798: The tramway opened with a single track having passing places.
August 1801 to October 1801: It is likely that there was limited construction work on the locks.
November 1802: It is believed that some groundwork for the locks was underway.
November 1803: Groundwork was complete and work started on building the locks.
August 1804: The locks were in an advanced state of completion.
13 October 1804: Locks 13, 14, 15 and 16 opened. These four locks gave Samuel Oldknow canal access to both the top and bottom of his newly built lime kilns.
October/November 1804: It is understood that construction of lock 6 was completed during this period. This was the last one to be completed but the locks were still not open throughout for navigation.
12 November 1805: Marple locks were open throughout on, or shortly before, this date. The most likely date lies somewhere between the first and twelfth day of November 1805. Although the locks were then open for trade, their construction was by no means complete.
February 1807: Marple Tramway closed.
June 1811: The Committee of the Peak Forest Canal Company, Thomas Brown (now the Consulting Engineer) and the Agent of Richard Arkwright Junior agreed that all construction work on Marple Locks was complete and that no further work was needed other than routine maintenance. Richard Arkwright Junior was the major financier for the construction of the locks.

 

Photographs: Author's Collection